Subject: [taskjuggler-devel] Re: Display of Tasks with subtasks
From: vincenegri <vince.negri () gmail ! com>
Date: 2005-11-07 13:55:23
Message-ID: 17fb.436f5cca () www ! taskjuggler ! org
[Download RAW message or body]
Quote:
> In the resulting Gantt chart, "foo" is shown as a rolled-up task, as it should be. \
> What I noticed, though, was that if I specify a desired start date for "foo", then \
> the rolled up task is always shown as starting on that date, even when none of the \
> sub-tasks start till later.
Of course, I now realise that by *not* giving a start date at all for the container \
task, I get the result I want. :blush:
.. but the behaviour when a start date is given still seems unintuitive to me. The \
key is the check against "depends.isEmpty()" in Task::scheduleContainer(). The \
current logic is this:
"If the earliest contained task has a date later then the defined start date of the \
container task, then change the start date of the container task *only if* it depends \
on another task."
I would have expected the start date of the container task to always be corrected to \
that of the earliest contained task.
--
To unsubscribe, email: taskjuggler-devel-unsubscribe@suse.com
For additional commands, email: taskjuggler-devel-help@suse.com
[prev in list] [next in list] [prev in thread] [next in thread]
Configure |
About |
News |
Add a list |
Sponsored by KoreLogic