Subject:    Re: kplato: Calculating schedule doesn't work
From:       Dag Andersen <danders () get2net ! dk>
Date:       2009-05-18 12:47:22
Message-ID: 200905181447.22292.danders () get2net ! dk
[Download RAW message or body]

[Attachment #2 (multipart/alternative)]


Mandag 18 maj 2009 13:16:25 skrev Vidar Langseid:
> Hi
>
> On Monday 18 May 2009 Dag Andersen wrote
>
> >Hi Vidar.
> >Your resource refer to calendar 'vl' which doesn't define any working
> > hours at all. If you define some working hours, or use the 'Base'
> > calendar instead it should work.
>
> Thanx. That was one missing link. I had totally overlooked the view for
> specifying that. Your email got me on the right track.
>
> Fixing the working hours makes the warnings/errors in the log to disappear.
> However, my four tasks (task1.1, task2.1,task2.2 and task2.3 ) are still
> scheduled in parallel (meaning that "vl" would need to work 400% in order
> to comply with the suggested plan while the limit is set to 100%).
> In View->Resource Assignments it only shows 8h a day.
It seems to work here.
Hmmm, did you create a new schedule or did you just recalculate the old one?
If you created a new, you'll have to select the correct schedule to view in 
the View menu. (It should list all schedules you have calculated) Also, the 
schedule name is shown in the status line (bottom right).
I know, this isn't fantastic, it's easy to forget/overlook, so I'm *very* open 
for suggestions of how to improve this!
>
> PS : Since you didn't CC me on the answer I had some problems answering to
> your email with correct reply-to headers, causing the threading to be
> wrong. I have now subscribed to the list so that shouldn't be a problem in
> the future.
>
> Best regards,
> Vidar
>
> On Monday 18 May 2009 10:37:07 am Vidar Langseid wrote:
> > Hi
> >
> > Sorry, but there must be something fundamental in kplato I have missed. I
> > hope someone might be able to help.
> > I have made one resource(person), one calendar and a few tasks which are
> > all assigned to the one resource.
> >
> > I then expect that when I hit the "Calculate" button that kplato would
> > schedule the tasks so that they don't overlap (the one resource I have
> > should only work 8 hours a day...). However this doesn't work.
> >
> > When I hit the "Calculate" button I instead get cryptic messages in the
> > log like:
> > "Could not  match effort. Want 16h0m got 0h0m"
> > "Resource vl available from 05/18/09 12:00am to 05/18/11 04:00pm"
> > "Resource vl not available in interval: 05/18/09 12:00am to 05/18/09
> > 04:00pm" All tasks is defined "As soon as possible", no fixed dates.
> >
> > Clicking on view->Resource assignments shows 0.0 in total for my resource
> > so there might some mapping between resource and tasks I have missed ?
> >
> > I have attached my test project in the email( not sure it will get
> > through to the mailing list though)
> >
> > I am using KOffice 2.0RC-1 from Kubuntu/Jaunty
> > (KPlato v.0.6.99)
> >
> > Best regards,
> > Vidar

-- 
Mvh.
Dag Andersen

[Attachment #5 (text/html)]

<!DOCTYPE HTML PUBLIC "-//W3C//DTD HTML 4.0//EN" \
"http://www.w3.org/TR/REC-html40/strict.dtd"><html><head><meta name="qrichtext" \
content="1" /><style type="text/css">p, li { white-space: pre-wrap; \
}</style></head><body style=" font-family:'Sans Serif'; font-size:10pt; \
font-weight:400; font-style:normal;">Mandag 18 maj 2009 13:16:25 skrev Vidar \
Langseid:<br> &gt; Hi<br>
&gt;<br>
&gt; On Monday 18 May 2009 Dag Andersen wrote<br>
&gt;<br>
&gt; &gt;Hi Vidar.<br>
&gt; &gt;Your resource refer to calendar 'vl' which doesn't define any working<br>
&gt; &gt; hours at all. If you define some working hours, or use the 'Base'<br>
&gt; &gt; calendar instead it should work.<br>
&gt;<br>
&gt; Thanx. That was one missing link. I had totally overlooked the view for<br>
&gt; specifying that. Your email got me on the right track.<br>
&gt;<br>
&gt; Fixing the working hours makes the warnings/errors in the log to disappear.<br>
&gt; However, my four tasks (task1.1, task2.1,task2.2 and task2.3 ) are still<br>
&gt; scheduled in parallel (meaning that "vl" would need to work 400% in order<br>
&gt; to comply with the suggested plan while the limit is set to 100%).<br>
&gt; In View-&gt;Resource Assignments it only shows 8h a day.<br>
It seems to work here.<br>
Hmmm, did you create a new schedule or did you just recalculate the old one?<br>
If you created a new, you'll have to select the correct schedule to view in the View \
menu. (It should list all schedules you have calculated) Also, the schedule name is \
shown in the status line (bottom right).<br> I know, this isn't fantastic, it's easy \
to forget/overlook, so I'm *very* open for suggestions of how to improve this!<br> \
&gt;<br> &gt; PS : Since you didn't CC me on the answer I had some problems answering \
to<br> &gt; your email with correct reply-to headers, causing the threading to be<br>
&gt; wrong. I have now subscribed to the list so that shouldn't be a problem in<br>
&gt; the future.<br>
&gt;<br>
&gt; Best regards,<br>
&gt; Vidar<br>
&gt;<br>
&gt; On Monday 18 May 2009 10:37:07 am Vidar Langseid wrote:<br>
&gt; &gt; Hi<br>
&gt; &gt;<br>
&gt; &gt; Sorry, but there must be something fundamental in kplato I have missed. \
I<br> &gt; &gt; hope someone might be able to help.<br>
&gt; &gt; I have made one resource(person), one calendar and a few tasks which \
are<br> &gt; &gt; all assigned to the one resource.<br>
&gt; &gt;<br>
&gt; &gt; I then expect that when I hit the "Calculate" button that kplato would<br>
&gt; &gt; schedule the tasks so that they don't overlap (the one resource I have<br>
&gt; &gt; should only work 8 hours a day...). However this doesn't work.<br>
&gt; &gt;<br>
&gt; &gt; When I hit the "Calculate" button I instead get cryptic messages in the<br>
&gt; &gt; log like:<br>
&gt; &gt; "Could not  match effort. Want 16h0m got 0h0m"<br>
&gt; &gt; "Resource vl available from 05/18/09 12:00am to 05/18/11 04:00pm"<br>
&gt; &gt; "Resource vl not available in interval: 05/18/09 12:00am to 05/18/09<br>
&gt; &gt; 04:00pm" All tasks is defined "As soon as possible", no fixed dates.<br>
&gt; &gt;<br>
&gt; &gt; Clicking on view-&gt;Resource assignments shows 0.0 in total for my \
resource<br> &gt; &gt; so there might some mapping between resource and tasks I have \
missed ?<br> &gt; &gt;<br>
&gt; &gt; I have attached my test project in the email( not sure it will get<br>
&gt; &gt; through to the mailing list though)<br>
&gt; &gt;<br>
&gt; &gt; I am using KOffice 2.0RC-1 from Kubuntu/Jaunty<br>
&gt; &gt; (KPlato v.0.6.99)<br>
&gt; &gt;<br>
&gt; &gt; Best regards,<br>
&gt; &gt; Vidar<br>
<p style="-qt-paragraph-type:empty; margin-top:0px; margin-bottom:0px; \
margin-left:0px; margin-right:0px; -qt-block-indent:0; text-indent:0px; \
-qt-user-state:0;"><br></p>-- <br> Mvh.<br>
Dag Andersen</p></body></html>



____________________________________
koffice mailing list
koffice@kde.org
To unsubscribe please visit:
https://mail.kde.org/mailman/listinfo/koffice


[prev in list] [next in list] [prev in thread] [next in thread] 

Configure | About | News | Add a list | Sponsored by KoreLogic