The differentiation is not so important.

  What is important for me, however, are the updated bookings: For example, if the \
initial estimate for an effort was 5d, but the actual time worked (as caputered in \
TaskJuggler's bookings) is more, this should be reflected in the updated ical output \
as well. And, this is done quite nicely for the XML output already. So, having the \
same 'information' in the ical would be sufficient for me. 

Does that make sense to you, or do I make a mistake here?

-- 
To unsubscribe, email the address listed in the List-Unsubscribe header
For additional commands, email: taskjuggler-help@suse.com


[prev in list] [next in list] [prev in thread] [next in thread] 

Configure | About | News | Add a list | Sponsored by KoreLogic