mschoell wrote on Mon, 21 November 2005 04:54
> Hello everybody,
>
> I'm looking for the solution of the following constraint.
>
> - Task A must be finished at least 2 Weeks before task B will be finished.
This is known as an end-to-end dependency. TaskJuggler does not support this \
directly. But you can model it with a milestone that follows both tasks and has a 2 \
week gap dependency on the 2nd task.
Quote:
> And another problem:
>
> - Task A must begin [at least / max ] 2 weeks before Task B ends.
> (ie simply a negative gap, which seems not to be possible)
>
> Is it possible to model such dependencies?
You can also model this with an extra milestone that both tasks depend on. The 1st \
task has a 2 week gap in the dependency.
Chris
--
TaskJuggler Developer
--
To unsubscribe, email the address listed in the List-Unsubscribe header
For additional commands, email: taskjuggler-help@suse.com
[prev in list] [next in list] [prev in thread] [next in thread]
Configure |
About |
News |
Add a list |
Sponsored by KoreLogic