Subject: [taskjuggler] Re: interactive report - percentage completed calculation
From: Chris Schlaeger <cs () suse ! de>
Date: 2005-10-09 16:30:29
Message-ID: 17a9.434945a5 () www ! taskjuggler ! org
[Download RAW message or body]
This is all expected (at least by me ;) behavior that you are seeing.
Having a booking after 'now' date (esp. in projection mode) does not make any sense. \
I will add a warning for this case. The purpose of the projection mode is to assume \
that all bookings are real done work. And 'now' is today. There can be no real done \
work in the future.
You have not specified any bookings for I1.plan so taskjuggler assumes that all work \
is happending according to plan. That's why you see progress (50% completion) even \
though you have not made any bookings. TaskJuggler is not transferring any effort \
from other tasks to this task.
Chris
--
TaskJuggler Developer
--
To unsubscribe, email the address listed in the List-Unsubscribe header
For additional commands, email: taskjuggler-help@suse.com
[prev in list] [next in list] [prev in thread] [next in thread]
Configure |
About |
News |
Add a list |
Sponsored by KoreLogic