Subject: [taskjuggler] Problem with task duration
From: LBroecker <Lars.Broecker () imk ! fraunhofer ! de>
Date: 2005-10-05 15:45:02
Message-ID: 17a6.4343f4fd () www ! taskjuggler ! org
[Download RAW message or body]
Hi!
I am trying to schedule a project, starting on 2005-10-01 and ending on 2008-10-01. I \
expected the duration of the project to read 3y, but the Project Overview says 4.2y \
in the duration column. Why ist that?
Furthermore, there is one task that is going to last the whole duration of the \
project. One resource will work 1/3 of its time on that task. So I would have \
expected the effort column for that task to read 1y, but instead I got 9m. I tried \
fiddling with the loadfactor of the resource, but increasing the load seems to \
increase expended effort in a discrete way, i.e. increasing the load in the interval \
between 0.34 and 0.37 did not change the effort, but increasing it to 0.38 resulted \
in a jump to 1.1y effort. I must be doing something wrong, but I cannot figure out \
what it is. Chris, can you help me there?
Regards,
Lars Bröcker
--
To unsubscribe, email the address listed in the List-Unsubscribe header
For additional commands, email: taskjuggler-help@suse.com
[prev in list] [next in list] [prev in thread] [next in thread]
Configure |
About |
News |
Add a list |
Sponsored by KoreLogic