From koffice Fri May 22 11:20:08 2009 From: Dag Andersen Date: Fri, 22 May 2009 11:20:08 +0000 To: koffice Subject: Re: kplato: Calculating schedule doesn't work Message-Id: <200905221320.09006.danders () get2net ! dk> X-MARC-Message: https://marc.info/?l=koffice&m=124299127003293 MIME-Version: 1 Content-Type: multipart/mixed; boundary="--===============0466497029==" --===============0466497029== Content-Type: multipart/alternative; boundary="Boundary-00=_opoFKRzJRkYYOrx" Content-Transfer-Encoding: 7bit Content-Disposition: inline --Boundary-00=_opoFKRzJRkYYOrx Content-Type: text/plain; charset="iso-8859-15" Content-Transfer-Encoding: 7bit Hi, All. This was a real kplato bug in the rc1 release. It is definitly present in kubuntu/jaunty packages, and most likely in any other distrubution also. It will be fixed in the next release. Thanks to Vidar for spotting it. -- Mvh. Dag Andersen ------------------------ Mandag 18 maj 2009 10:37:07 skrev Vidar Langseid: > Hi > > Sorry, but there must be something fundamental in kplato I have missed. I > hope someone might be able to help. > I have made one resource(person), one calendar and a few tasks which are > all assigned to the one resource. > > I then expect that when I hit the "Calculate" button that kplato would > schedule the tasks so that they don't overlap (the one resource I have > should only work 8 hours a day...). However this doesn't work. > > When I hit the "Calculate" button I instead get cryptic messages in the log > like: > "Could not match effort. Want 16h0m got 0h0m" > "Resource vl available from 05/18/09 12:00am to 05/18/11 04:00pm" > "Resource vl not available in interval: 05/18/09 12:00am to 05/18/09 > 04:00pm" All tasks is defined "As soon as possible", no fixed dates. > > Clicking on view->Resource assignments shows 0.0 in total for my resource > so there might some mapping between resource and tasks I have missed ? > > I have attached my test project in the email( not sure it will get through > to the mailing list though) > > I am using KOffice 2.0RC-1 from Kubuntu/Jaunty > (KPlato v.0.6.99) > > Best regards, > Vidar --Boundary-00=_opoFKRzJRkYYOrx Content-Type: text/html; charset="iso-8859-15" Content-Transfer-Encoding: 7bit Hi, All.
This was a real kplato bug in the rc1 release. It is definitly present in kubuntu/jaunty packages, and most likely in any other distrubution also.
It will be fixed in the next release.


Thanks to Vidar for spotting it.


--
Mvh.
Dag Andersen


------------------------
Mandag 18 maj 2009 10:37:07 skrev Vidar Langseid:
> Hi
>
> Sorry, but there must be something fundamental in kplato I have missed. I
> hope someone might be able to help.
> I have made one resource(person), one calendar and a few tasks which are
> all assigned to the one resource.
>
> I then expect that when I hit the "Calculate" button that kplato would
> schedule the tasks so that they don't overlap (the one resource I have
> should only work 8 hours a day...). However this doesn't work.
>
> When I hit the "Calculate" button I instead get cryptic messages in the log
> like:
> "Could not match effort. Want 16h0m got 0h0m"
> "Resource vl available from 05/18/09 12:00am to 05/18/11 04:00pm"
> "Resource vl not available in interval: 05/18/09 12:00am to 05/18/09
> 04:00pm" All tasks is defined "As soon as possible", no fixed dates.
>
> Clicking on view->Resource assignments shows 0.0 in total for my resource
> so there might some mapping between resource and tasks I have missed ?
>
> I have attached my test project in the email( not sure it will get through
> to the mailing list though)
>
> I am using KOffice 2.0RC-1 from Kubuntu/Jaunty
> (KPlato v.0.6.99)
>
> Best regards,
> Vidar



--Boundary-00=_opoFKRzJRkYYOrx-- --===============0466497029== Content-Type: text/plain; charset="us-ascii" MIME-Version: 1.0 Content-Transfer-Encoding: 7bit Content-Disposition: inline ____________________________________ koffice mailing list koffice@kde.org To unsubscribe please visit: https://mail.kde.org/mailman/listinfo/koffice --===============0466497029==--