On Monday 18 May 2009 Dag Andersen wrote
>Hi Vidar.
>Your resource refer to calendar 'vl' which doesn't define any working hours
> at all. If you define some working hours, or use the 'Base' calendar
> instead it should work.
Thanx. That was one missing link. I had totally overlooked the view for 
specifying that. Your email got me on the right track.

Fixing the working hours makes the warnings/errors in the log to disappear.
However, my four tasks (task1.1, task2.1,task2.2 and task2.3 ) are still 
scheduled in parallel (meaning that "vl" would need to work 400% in order to 
comply with the suggested plan while the limit is set to 100%).
In View->Resource Assignments it only shows 8h a day.

PS : Since you didn't CC me on the answer I had some problems answering to 
your email with correct reply-to headers, causing the threading to be wrong. I 
have now subscribed to the list so that shouldn't be a problem in the future.

Best regards,
Vidar

On Monday 18 May 2009 10:37:07 am Vidar Langseid wrote:
> Hi
>
> Sorry, but there must be something fundamental in kplato I have missed. I
> hope someone might be able to help.
> I have made one resource(person), one calendar and a few tasks which are
> all assigned to the one resource.
>
> I then expect that when I hit the "Calculate" button that kplato would
> schedule the tasks so that they don't overlap (the one resource I have
> should only work 8 hours a day...). However this doesn't work.
>
> When I hit the "Calculate" button I instead get cryptic messages in the log
> like:
> "Could not  match effort. Want 16h0m got 0h0m"
> "Resource vl available from 05/18/09 12:00am to 05/18/11 04:00pm"
> "Resource vl not available in interval: 05/18/09 12:00am to 05/18/09
> 04:00pm" All tasks is defined "As soon as possible", no fixed dates.
>
> Clicking on view->Resource assignments shows 0.0 in total for my resource
> so there might some mapping between resource and tasks I have missed ?
>
> I have attached my test project in the email( not sure it will get through
> to the mailing list though)
>
> I am using KOffice 2.0RC-1 from Kubuntu/Jaunty
> (KPlato v.0.6.99)
>
> Best regards,
> Vidar

-- 
vl@ez.no | eZ systems | ez.no
____________________________________
koffice mailing list
koffice@kde.org
To unsubscribe please visit:
https://mail.kde.org/mailman/listinfo/koffice
[prev in list] [next in list] [prev in thread] [next in thread] 

Configure | About | News | Add a list | Sponsored by KoreLogic