[prev in list] [next in list] [prev in thread] [next in thread] 

List:       koffice
Subject:    Re: kplato; show actual planning
From:       Dag Andersen <danders () get2net ! dk>
Date:       2009-04-02 8:17:28
Message-ID: 200904021017.28504.danders () get2net ! dk
[Download RAW message or body]

[Attachment #2 (multipart/alternative)]


On Onsdag 25 marts 2009 19:33:16 Thomas Zander wrote:
> I've been playing with KPlato from KOffice2.0 (thanks fly to Alexis) and
> there are 2 questions I have on its usage;
> * First is if I have a project. I added various tasks and made them into a
> scheduled list of items then I can calculate the schedule.
> It will schedule the tasks and put them on a timeline so I can see exactly
> when each tasks starts and ends.
>
> Now, if I then go and update each task as time goes by I end up with the
> actually taken time per task. This can be less than the planned time, or
> more.
> Question; how do I show the updated schedule with the new times ?
If you mean actual start/finish, you can't (yet?). You can have %completion 
shown by rightclick in treeview and select the info you want to show.
In general, you can configure most views this way.
>
> Another Question; I think it would be useful to create more than one
> schedule with different parameters. For example I would have a schedule
> that is the pessimistic timeline and another that is the optimistic one.
> I can't seem to find out how to do that (it used to be possible AFAIK).
The optimistc/pessimistic schedules from the last release didn't make it into 
this release. I had originally thought of using them for some analyzis 
purposes, but came to the conclution that it's better to implement a monte 
carlo simulation and take it from there.

The intention with multiple sechedules are twofold:
1) Calculation with different parameters. Not many parameters to tweek yet, 
so...
2) Reschedule running projects when there are changes to resource 
availability, new tasks or the progress is just too far of the plan.
You this by adding a sub-schedule and calculate that. It will reschedule the 
tasks not yet finished taking into account the reported progress/remaining 
effort.
>
> Thanks for any help!

-- 
Mvh.
Dag Andersen

[Attachment #5 (text/html)]

<!DOCTYPE HTML PUBLIC "-//W3C//DTD HTML 4.0//EN" \
"http://www.w3.org/TR/REC-html40/strict.dtd"><html><head><meta name="qrichtext" \
content="1" /><style type="text/css">p, li { white-space: pre-wrap; \
}</style></head><body style=" font-family:'Sans Serif'; font-size:10pt; \
font-weight:400; font-style:normal;">On Onsdag 25 marts 2009 19:33:16 Thomas Zander \
wrote:<br> &gt; I've been playing with KPlato from KOffice2.0 (thanks fly to Alexis) \
and<br> &gt; there are 2 questions I have on its usage;<br>
&gt; * First is if I have a project. I added various tasks and made them into a<br>
&gt; scheduled list of items then I can calculate the schedule.<br>
&gt; It will schedule the tasks and put them on a timeline so I can see exactly<br>
&gt; when each tasks starts and ends.<br>
&gt;<br>
&gt; Now, if I then go and update each task as time goes by I end up with the<br>
&gt; actually taken time per task. This can be less than the planned time, or<br>
&gt; more.<br>
&gt; Question; how do I show the updated schedule with the new times ?<br>
If you mean actual start/finish, you can't (yet?). You can have %completion shown by \
rightclick in treeview and select the info you want to show.<br> In general, you can \
configure most views this way.<br> &gt;<br>
&gt; Another Question; I think it would be useful to create more than one<br>
&gt; schedule with different parameters. For example I would have a schedule<br>
&gt; that is the pessimistic timeline and another that is the optimistic one.<br>
&gt; I can't seem to find out how to do that (it used to be possible AFAIK).<br>
The optimistc/pessimistic schedules from the last release didn't make it into this \
release. I had originally thought of using them for some analyzis purposes, but came \
to the conclution that it's better to implement a monte carlo simulation and take it \
from there.<br> <p style="-qt-paragraph-type:empty; margin-top:0px; \
margin-bottom:0px; margin-left:0px; margin-right:0px; -qt-block-indent:0; \
text-indent:0px; -qt-user-state:0;"><br></p>The intention with multiple sechedules \
are twofold:<br> 1) Calculation with different parameters. Not many parameters to \
tweek yet, so...<br> 2) Reschedule running projects when there are changes to \
resource availability, new tasks or the progress is just too far of the plan.<br> You \
this by adding a sub-schedule and calculate that. It will reschedule the tasks not \
yet finished taking into account the reported progress/remaining effort.<br> &gt;<br>
&gt; Thanks for any help!<br>
<p style="-qt-paragraph-type:empty; margin-top:0px; margin-bottom:0px; \
margin-left:0px; margin-right:0px; -qt-block-indent:0; text-indent:0px; \
-qt-user-state:0;"><br></p>-- <br> Mvh.<br>
Dag Andersen</p></body></html>



____________________________________
koffice mailing list
koffice@kde.org
To unsubscribe please visit:
https://mail.kde.org/mailman/listinfo/koffice


[prev in list] [next in list] [prev in thread] [next in thread] 

Configure | About | News | Add a list | Sponsored by KoreLogic