On Thursday 30 October 2003 07:37, Kevin Donnelly wrote: > Can somebody just confirm to me, now that the string freeze is in effect, how > long there is to complete revision of the i18n translation before that too is > frozen? > > http://developer.kde.org/development-versions/kde-3.2-release-plan.html says > that the last i18n commits are to be in Week 47, so if Week 50 means 8 > December, then Week 47 should mean that all translations need to be committed > by 17 November. No. The week number refers to the weekend. So the last day is 22nd BTW: I'd like every translator with CVS access to double check his commits. I could daily clean out compilation errors, errors found by check_po_files, etc. This really shouldn't happen in the remaining weeks. Greetings, Stephan -- There may be no I in TEAM, but a M and an E.