SVN commit 465219 by coolo: After the feedback I received, I decided this: We do a 3.4.3 first M +6 -0 kde-3.4-release-plan.html M +17 -6 kde-3.5-release-plan.html --- trunk/developer.kde.org/development-versions/kde-3.4-release-plan.html #465218:465219 @@ -70,6 +70,12 @@

Wednesday July 27th, 2005: Targeted 3.4.2 Release date

+

Wednesday October 5th, 2005: Creating tags/KDE/3.4.3/

+ The third translation and bug fix release. + Please add your changes to trunk/www/announcements/changelogs/changelog3_4_2to3_4_3.php. + +

Wednesday October 12th, 2005: Targeted 3.4.3 Release date

+

Frequently Asked Questions

What's the deal with that feature-plan?

--- trunk/developer.kde.org/development-versions/kde-3.5-release-plan.html #465218:465219 @@ -30,19 +30,30 @@ After this date the same message freeze applies as for released versions (i.e. only previously untranslated strings or clear errors in strings can be fixed - no new strings) -

September 10th, 2005: tags/KDE/3_5_beta1 created

+

September 10th, 2005: tags/KDE/3.5-beta1 created

The 3.5 branch is tagged as Beta 1 and is frozen for nonurgent commits till 14th.

September 13th, 2005: Beta1 is prepared

Beta 1 is prepared and released after some initial testing. The incoming bugs will be reviewed for their severity. -

After that?

- We don't know yet how things develop and the Akademy event might change something unforseen. So - I would prefer to leave it open if we have a second beta or release right after beta1. I would - guess, we don't need a second one for KDE 3.5. So the targeted release day would be towards end - of october (4 weeks of giving beta1 testing, one or two weeks for RCs - release) +

October 9th, 2005: tags/KDE/3.5-beta2 created

+ The 3.5 branch is tagged as Beta 2 and is frozen for nonurgent commits till 12th. +

October 12th, 2005: Beta2 is prepared

+ Beta 2 is prepared and released after some initial testing. + The incoming bugs will be reviewed for their severity. + +

November 7th, 2005: Total release freeze

+ This is the very last for commiting anything that isn't reviewed on the + development lists. If in doubt, ask the release coordinator. + +

November 9th, 2005: Release Candidate 1

+ We will release 3.5.0 as first release candidate and then wait for show stoppers + to appear. + +

November 23rd, 2005: Targetted Release Date

+

Frequently Asked Questions

What's the deal with that feature-plan?