Subject: Re: 2401bis schedule
From: Stephen Kent <kent () bbn ! com>
Date: 2003-11-25 22:56:29
[Download RAW message or body]
At 14:46 -0500 11/25/03, Mark Duffy wrote:
>>Proposed timeline for 2401bis from the WG chairs
>> Close all issues by Nov. 30th
>> Final draft of by December 15
>> Start WG last call December 15 through January 10
>
>I'll admit I was surprised when I first saw the above timeline. Do
>the chairs think this is feasible? Do the authors? Do the other
>participants?
the authors also have expressed reservations about the time line :-)
We will continue to work the issues, but we also do plan to release a
version of 2401bis by mid-December. I doubt that it will be the last
version.